PT . SULZER HICKAM INDONESIA

RECONDITION OF BRUSH 23500 KVA TURBINE GENERATOR UNIT #1 PT. TATA JABAR - POWER PLANT

GENERAL SCOPE OF WORK

1. Pre-Inspection before shut down 
2. Dismantle unit of Generator 
3. Pull out main rotor from stator 
4. Electrical and Mechanical Inspection
5. Clean and Inspec all generator components
6. Electrical test of stator, rotor winding & exciter
7. Fit new stator wedges
8. Dry out and spray stator winding with air sry varnish
9. Inserting Rotor to Stator 
10. Completed re-assembly generator 
11. Laser alignment generator with turbine
12. Commisionong test and completion all reported